Local Transport Plan and Other DFT Funding
The different authorities in the West Yorkshire are working together to ensure that West Yorkshire’s transport system connects people and places in ways that support the economy, the environment and quality of life.
The objectives of the plan are:
- To improve connectivity to support economic activity and growth in West Yorkshire and the Leeds City Region
- To make substantial progress towards a low carbon, sustainable transport system for West Yorkshire, while recognising transport's contribution to national carbon reduction plans
- To enhance the quality of life of people living in, working in and visiting West Yorkshire
Projects within this plan
Browse the different projects within this plan by opening and closing the tabs below.
- Cycle City Ambition Grant (CCAG)
-
The £60 million programme is funded through the Department for Transport’s Cycle City Ambition Grant and local match funding. It aims to:
- Make cycling a natural and popular choice for short journeys
- Make cycling accessible to everyone
- Improve access to employment, skills and education
- Reduce CO2 and improve local air quality
- Create a safe environment for walking and cycling
Infrastructure projects that have been built now include the 14km segregated Cycle Superhighway running from Leeds city centre along the A647 to the new Broadway shopping centre right in the heart of Bradford.
CityConnect is delivered in partnership by West Yorkshire Combined Authority, the five West Yorkshire councils and City of York Council.
Last updated Q1 2023/24
- One System Public Transport
-
We want to create a world class public transport system that connects different modes of transport seamlessly into one comprehensive, easy-to-use network.
We aim to transform the performance, image and experience of public transport to make it an attractive choice for all.
Rail is currently the backbone of our mass transit network. Where the service is frequent and with newer trains, the number of commuters using rail is high. We want to replicate this high quality service across the City Region.
Buses are currently the most used form of public transport and we need to ensure there is better integration between these two modes including physical interchange, timetabling, ticketing and payment. We have an ambition to build on our current public transport networks and we will set out a plan for how different modes, including rail, mass transit and bus rapid transit, can unlock economic growth constraints.
We recognise the benefits of segregating public transport from other road vehicles and will look at key corridors for where this could be developed further. More people are now travelling between districts to access work opportunities.
We need our public transport system to be High Speed ready. We will link to and build on national investment in High Speed Rail and Northern Powerhouse Rail proposals and we will align our public transport investment with improvements to the motorways and our local roads for a truly integrated transport system. Only through improving our public transport offer, be that bus, rail, park and ride, mass transit or other modes, will we be able to achieve our economic objectives at the same time as ensuring that our towns and city centres are places that promote health, wellbeing and attract inward investment.
- Rail Strategy
-
The Local Transport Plan Strategy from 2011 – 2026 has a vision to develop a transport system that gives people access to what they want easily, efficiently and in a way that supports the environment, the economy and quality of life. A new approach to rail in West Yorkshire and the wider Leeds City Region is needed if rail is to play a greater role in a modern and dynamic City Region low carbon economy
The Combined Authority will work with partners such as PTEG, all northern PTEs, the Department for Transport, Train Operating Companies, Network Rail, the ORR and the McNulty Review team to ensure that this opportunity will enable the rail offer in West Yorkshire to modernise and play its part in a successful transport system over the long term. The following proposals will be delivered through the rail strategy:
- Additional rail capacity
- Improve operational performance
- Improve customer service quality standards
- Modernise the rail offer
- Improve journey times
- Improve integration between modes
- Integrate ticketing
- Improve service patterns and frequency
- Reduce the carbon footprint of the train
- West Yorkshire Transport Asset Management Plan
-
The West Yorkshire Transport Asset Management Plan sets the guidelines as to how transport assets are maintained, and how they will be maintained in the future.
Transport asset management is about more than just maintaining our roads. There are bridges, traffic control systems, street lighting and public transport infrastructure that requires investment to deal with current and future demands. While our customer satisfaction surveys tells us that the travelling public rate roads and our other assets as being 'very important', these people also express dissatisfaction with their condition.
Potholes, defective roads and poor quality cycle tracks and footways can create inconvenience, affect the quality of journeys and incur costs on users but also present potential hazards to our more vulnerable road users such as motorcyclists, cyclists and pedestrians.
Although research shows that poorly maintained roads fall into a deeper state of disrepair contributing to traffic delays and disruption, the under investment in highway maintenance by successive governments means managing our transport assets presents a major challenge. We have a backlog of repairs and there is a growing gap between the costs of the repairs and the funding that is available. We must make our approach to, and funding for asset management work better.
Network North – additional highway maintenance funding
Highway authorities across England are to benefit from a boost in funding for local highway maintenance.
As part of an announcement on Network North funding in October 2023, an increase in funding for local highway maintenance was given in order to make real improvements in road condition. The funding is intended to allow more of our roads to be resurfaced, more of our bridges to be repaired, and other highway assets to be fixed than would we otherwise be able to achieve.
As part of this additional funding, we have been asked by DfT to publish a summary of the additional resurfacing work we will deliver with the new funding over the next 2 years.
For both 2023/24 and 2024/25 we are receiving an additional £4.633m per year for local highways maintenance.
The programmes are still being finalised and will undergo final approvals both locally in each council and at a combined authority committee in early Summer in order to release the funding and deliver the whole p2 year programme. In the meantime, the programme below is a draft representation of what roads/areas will be targeted (and are subject to change).
This additional funding complements the already approved CRSTS Highways Asset Management programme in West Yorkshire that was approved at CA in July 2023.
Bradford
Areas / roads where work is planned Type of works being undertaken on asset group Indicative cost Surface area resurfaced (if applicable) m2 Benefits from it B6381 Barkerend Road
Road resurfacing
£70,000
2,000
Improve the asset condition of a key bus and commuter route
C111 Cutler Heights Lane
Road resurfacing
£170,000
4,400
As above
B6379 Town Gate, Wyke
Road resurfacing
£160,000
4,000
Improve the asset condition of a local high street
C111 High Street, Wibsey
Road resurfacing
£90,000
2,200
As above
Royd Wood Terr, Cullingworth, Bingley Rural
Bus Turning Circle
£11,000
800
Improvements to public transport (bus turning circle)
Brantcliffe Way, Baildon
Road resurfacing
£12,000
195
Improve the asset condition
Merville Avenue, Baildon
Road resurfacing
£10,000
638
As above
New Close Road, Nab Wood
Road resurfacing
£40,000
2,400
As above
Mary St / Minorca Mount, Denholme
Road resurfacing
£18,000
1,900
Improve the asset condition and access to local school
Thornacre Road, Wrose
Road resurfacing
£30,000
2,300
Improve the asset condition
Back Grangefield Ave, Burley
Road resurfacing
£23,000
2,300
As above
Back Lawn Ave, Burley
Road resurfacing
£22,000
720
As above
Back Norwood Terrace, Burley
Road resurfacing
£10,000
480
As above
Rocklands Place, Baildon
Road resurfacing
£5,000
290
Surface treatment to halt deterioration and enhance road safety
Spring Close, Gilstead
Micro Asphalt
£3,000
470
As above
Low Close, Gilstead
Micro Asphalt
£3,000
430
As above
The Robins, Burley
Micro Asphalt
£8,000
2,244
As above
Suresnes Road, Keighley
Road resurfacing
£40,000
3,930
Improve the asset condition
Reservoir Road, Stanbury
Road resurfacing
£55,000
4,300
As above
Belle Vue, Ilkley
Road resurfacing
£15,000
1,500
As above
Wheathead Lane, Keighley
Road resurfacing
£48,000
As above
Granby Lane, Keighley
Road resurfacing
£35,000
2,147
As above
Howden Road, Silsden
Road resurfacing
£22,000
1,200
As above
Bradford South
Carriageway patching
£78,000
Repair deterioration in the short term in order to reduce future maintenance needs / disruption
Bradford South
Carriageway and footway slurry / micro asphalt
£40,000
Surface treatment to halt deterioration and enhance road safety
Bradford East
Carriageway patching
£78,000
Repair deterioration in the short term in order to reduce future maintenance needs / disruption
Bradford East
Carriageway and footway slurry / micro asphalt
£40,000
Surface treatment to halt deterioration and enhance road safety
Bradford West
Carriageway patching
£78,000
Repair deterioration in the short term in order to reduce future maintenance needs / disruption
Bradford West
Carriageway and footway slurry / micro asphalt
£40,000
Surface treatment to halt deterioration and enhance road safety
Shipley Ward Unclassified Road Resurfacing
Unclassified road resurfacing
£155,000
As above
Shipley Ward Carriageway Pathcing
Carriageway patching
£85,000
Wider patching of asset deterioration areas to reduce future maintenance needs and disruption
Footways repairs in Shipley Ward
Footway slurry sealing / resurfacing)
£70,000
Improved pedestrian footway asset condition
Keighley constituency unclassified road resurfacing
Unclassified road resurfacing
£175,000
Surface treatment to halt deterioration and enhance road safety
Keighley constituency footway repairs
Carriageway patching
£85,530
Wider patching of asset deterioration areas to reduce future maintenance needs and disruption
Keighley constituency unclassified road resurfacing
Footway slurry sealing / resurfacing)
£75,000
Improved pedestrian footway asset condition
Total spend: £1,899,530
Calderdale
Areas / roads where work is planned
Type of works being undertaken on asset group
Indicative cost (£)
Surface area resurfaced (if applicable) m2
Benefits from it
Status
Holmes Road
Resurfacing
£265,000
Asset life renew. Improved journey times. Cycling and pedestrian saftey.
Complete 23-24
River Street, Mission Street, Calder Street
Resurfacing
£350,000
Asset life renew. Improving industrial access.
Complete 23-24
C42 (Akroyd Lane, Billy Lane, Nook Lane)
Resurfacing
496,920
14,300
Asset life renew. Improved journey times. Safety.
Programmed 24-25
Total spend: £1,111,920
Kirklees
Areas / roads where work is planned
Type of works being undertaken on asset group
Indicative cost (£)
Surface area resurfaced (if applicable) m2
Benefits from it
Greenhead, Almondbury, Netherton
Footway resurfacing
£ 225,000.00
4000
Improved walking surface delivering connectivity supporting active travel
Golcar, Staincliffe, Batley, Scholes, Ashbrow
Carriageway resurfacing
£ 895,000.00
16500
Improved condition, ride quality, reduced emissions
Various
Micro resurfacing
£200,000
20000
As above
Rural areas
Velocity/jet patching
£200,000
As above
As per footway schemes
Street Lighting
£25,000
20 number column replacements as a part of F/W works
Asset replacment/renewal
As per carriageway schemes
Drainage
£50,000
Repair works as a part of c/way resurfacing schemes
Asset replacment/renewal/ climate mitigation ensuring the drainage system is fully functional
Across the district
Find and fix potholes
£248,934
Improve network condition reduce risk of third party claims, improve public perception
Total spend: £1,843,934
Leeds
Areas / roads where work is planned
Type of works being undertaken on asset group
Indicative cost
Surface area resurfaced (if applicable) m2
Benefits from it
Status
LRS17Recreation Place
Kerb, Footway & Carrigeway Works
£51,052
1676
Improved condition: Ride quality, walking surface
Complete 2023/24
LRS18Recreation Street
Kerb, Footway & Carrigeway Works
£34,841
1562
Complete 2023/24
LRS26Wellington Grove
Kerb, Footway & Carrigeway Works
£67,706
2059
As above
Complete 2023/24
LRS27Appleton Way
Carriageway Works
£116,494
1337
Improved condition: Ride quality
Complete 2023/24
LRS42Mill Green Place
Carriageway and Footway Works
£103,918
3607
Improved condition: Ride quality, walking surface
Complete 2023/24
LRS69Whack House Close
Kerb, Footway & Carrigeway Works
£35,571
1207
As above
Complete 2023/24
LRS77Knott Lane
Kerb, Footway & Carrigeway Works
£126,784
3053
As above
Complete 2023/24
LRS84Foundry Mill Street
Carriageway and Footway Works
£116,013
3351
As above
Complete 2023/24
LRS85Foundry Mill Street
Kerb, Footway & Carrigeway Works
£53,093
1775
As above
Complete 2023/24
LRS86Foundry Mill Street
Carriageway Works
£42,986
616
Improved condition: Ride quality
Complete 2023/24
LRS90Poole Road
Carriageway Works
£20,093
686
As above
Complete 2023/24
LRS98Abbeydale Mount
Kerb, Footway & Carrigeway Works
£53,793
1349
Improved condition: Ride quality, walking surface
Complete 2023/24
LRS124Queenshill Crescent
Carriageway Works
£37,527
1309
Improved condition: Ride quality
Complete 2023/24
LRS125Stainburn Avenue
Carriageway Works
£32,448
1785
As above
Complete 2023/24
LRS126Kingsdale Gardens
Kerb, Footway & Carrigeway Works
£64,852
3649
Improved condition: Ride quality, walking surface
Complete 2023/24
LRS130Wynyard Drive
Carriageway Works
£106,715
1827
Improved condition: Ride quality
Complete 2023/24
LRS131Wynyard Drive
Carriageway and Footway Works
£69,757
3181
Improved condition: Ride quality, walking surface
Complete 2023/24
LRS141Chandos Avenue
Carriageway and Footway Works
£78,136
3451
As above
Complete 2023/24
LRS143West Park Road
Kerb, Footway & Carrigeway Works
£66,245
3110
As above
Complete 2023/24
LRS149Moor Road
Carriageway and Footway Works
£93,814
3351
As above
Complete 2023/24
LRS154Sandbeck Lane
Carriageway Works
£86,812
3045
Improved condition: Ride quality
Complete 2023/24
NN1Pontefract Road
Carriageway Works
£252,818
5327
As above
Delivery Due 2024/25
NN2Dibb Lane
Carriageway Works
£61,584
791
As above
Delivery Due 2024/25
NN3Kirk Lane
Carriageway Works
£29,156
1946
As above
Delivery Due 2024/25
NN4New Road
Carriageway Works
£121,800
4865
As above
Delivery Due 2024/25
NN5Milners Road
Carriageway Works
£38,694
497
As above
Delivery Due 2024/25
NN6King Lane
Carriageway Works
£26,849
2282
As above
Delivery Due 2024/25
NN7Arthington Road
Carriageway Works
£27,178
2310
As above
Delivery Due 2024/25
NN8Arthington Road
Carriageway Works
£35,661
3031
As above
Delivery Due 2024/25
NN9Commercial Street
Carriageway Works
£145,954
1554
As above
Delivery Due 2024/25
NN10Church Street
Carriageway Works
£28,703
588
As above
Delivery Due 2024/25
NN11Duncan Street
Carriageway Works
£14,819
714
As above
Delivery Due 2024/25
NN12New Market Street
Carriageway Works
£15,109
728
As above
Delivery Due 2024/25
NN13Buckstone Road
Kerb, Footway & Carrigeway Works
£180,838
2883
Improved condition: Ride quality, walking surface
Delivery Due 2024/25
NN14Haddon Road
Kerb, Footway & Carrigeway Works
£289,635
3380
As above
Delivery Due 2024/25
NN15Wellstone Rise
Kerb, Footway & Carrigeway Works
£182,074
3465
As above
Delivery Due 2024/25
Total spend: £2,909,524
Wakefield
Areas / roads where work is planned
Type of works being undertaken on asset group
Indicative cost
Surface area resurfaced (if applicable) m2
Benefits from it
A650 Wrenthorpe Bypass, Wrenthorpe & Outwood
Resurface
£120,497
3012
Vision zero strategic objective for safer roads, A well maintained highway provides a safe, attractive and efficient network for all highway users, and to support decarbonisation targets and specific council corporate objectives
Places to be proud of
An economy that works for everyone
Better health and lives
Thriving children and families
A greener Wakefield districtBarnsley Road South Elmsall and South Kirby
Resurface
£211,044
5276
As above
Pasture Way Roundabout, Altofts & Whitwood
Resurface
£32,745
819
As above
Standbridge Lane, Wakefield South
Resurface
£32,891
822
As above
Hemsworth A1 Link Road, Ackworth, North Elmsall and Upton
Surface Dressing
£184,371
39446
As above
Cutsyke Road, Altofts & Whitwood
Surface Dressing
£18,546
3968
As above
Aketon Road, Altofts & Whitwood
Surface Dressing
£32,836
7025
As above
Lock Lane, Castleford Central & Glasshoughton
Surface Dressing
£27,656
5917
As above
Holywell Lane, Castleford Central & Glasshoughton
Surface Dressing
£42,248
9039
As above
Bleakley Lane, Crofton, Ryhill & Walton
Surface Dressing
£23,156
4954
As above
Chevet Lane, Crofton, Ryhill & Walton
Surface Dressing
£98,683
21113
As above
Station Lane, Featherstone
Surface Dressing
£13,305
2846
As above
Green Lane, Featherstone
Surface Dressing
£15,344
3283
As above
Featherstone Lane, Featherstone
Surface Dressing
£35,223
7536
As above
Willow Lane, Featherstone
Surface Dressing
£11,193
2395
As above
Cutsyke Road, Featherstone
Surface Dressing
£43,554
9318
As above
Wesley Street, Ossett
Surface Dressing
£21,550
4611
As above
Aberford Road, Stanley & Outwood East
Surface Dressing
£100,425
21486
As above
Huddersfield Road, Wakefield Rural
Surface Dressing
£112,900
24155
As above
Netherton Lane, Wakefield Rural
Surface Dressing
£61,098
13072
As above
Hostingley Lane, Wakefield Rural
Surface Dressing
£23,436
5014
As above
Hardcastle Lane, Wakefield Rural
Surface Dressing
£11,466
2453
As above
Old Road, Wakefield Rural
Surface Dressing
£57,032
12202
As above
District Wide
Reactive repairs identified through routine inspections
£169,895
Support the move towards more sustainable, first-time permanent repairs of defects identified during the routine inspections. Increase embodied carbon savings from road maintenance and reduced network disruption.
Total spend: £1,501,092
How is your authority introducing innovation in the delivery of highways maintenance (eg the use of new equipment or software) and where it plans to go further:
The collective West Yorkshire Highway Information Asset Management Group continue to review new materials and methods that look to offer more cost effective, lower carbon and faster delivery in order to increase maintenance and renewal of the highways network in the region.
We are targeting more preventative maintenance practices to slow deterioration in order to protect the wider highway assets and increase activities over a wider area as well as targeting route causes such as drainage defects that if left cause damage to roads and pavements.
Wakefield have engaged with their Technical & digital transformation team to develop an AI output for street level surveys utilising attachments to Street Services refuse vehicles which cover over 95% of the districts roads and could provide street level surveys using machine learned models i.e. colour and shape deviation that can detect defects and gully conditions. These will enhance the service of the survey technicians with a view in due course to manage AI into the asset management policy. The project is in the Alpha phase but could be expected to be operational in 25/26.
West Yorkshire council highways teams and West Yorkshire Combined Authority are also looking to develop a new asset deterioration model to better track condition and plan timely interventions to maximise the benefits from the funding allocations we receive for highway asset maintenance activities.
What steps are your authority taking to ensure utility works are completed in an organised and efficient manner:
Street works and roadworks continue to be regulated by the New Roads and Street Works 1991 (NRASWA and the Traffic Management Act 2004 (TMA) and the related codes of practice and statutory instruments.
The Yorkshire Common Permit Scheme was developed and implemented in conjunction with the other four West Yorkshire Authorities and Barnsley and Sheffield councils. It was one of the first permit schemes introduced in England outside London. The YCPS applied to just the busiest roads across the district. Non-permit streets continued to be dealt with under the earlier noticing system. The YCPS was changed in March 2020 to apply to all adopted roads, becoming an individual permit scheme known as the Kirklees Council Permit Scheme.
The permit scheme covers co-ordination, inspection, restrictions, sanctions and charges, however there are still issues where statutory undertakers come along and stipulate emergency works that either delay vital maintenance work, or worse still mean excavations in recently delivered projects (despite all long-term notifications and protection notices being in place).
The 5 partner councils continue to develop better relationships with statutory undertakers and the CA will join more strategic level coordination on the back of Network North funding levels to ensure we have a step change in the condition of the network.